Multan Avenue Project Approved: Rs2.8 Billion Road to Be Completed in Four Months

The Multan Avenue Project, one of the most important urban infrastructure developments in South Punjab, has officially received approval, and its completion date has been unveiled. The Multan Divisional Development Working Party (DDWP) has approved the nine-kilometre-long Multan Avenue project with a total estimated cost of Rs 2.8 billion.
According to officials, the project stretches from Saidanwala Chowk to Sahu Chowk and is expected to be completed within four months. Once completed, the project will significantly improve traffic flow, urban mobility, road safety, and environmental sustainability in Multan.
Multan Avenue Project Approved by DDWP
The approval of the Multan Avenue project by the DDWP marks a major milestone for the city’s development. The project is part of the government’s broader plan to modernize road infrastructure and improve the quality of life for residents.
Key Approval Details
- Project length: 9 kilometres
- Total cost: Rs 2.8 billion
- Approved by: Multan Divisional Development Working Party (DDWP)
- Completion timeline: 4 months
The project is designed to meet modern urban development standards while addressing Multan’s growing traffic and population needs.
Route Details: From Saidanwala Chowk to Sahu Chowk
The Multan Avenue project will cover a crucial corridor of the city, connecting Saidanwala Chowk to Sahu Chowk.
Importance of This Route
- High daily traffic volume
- Key connection between residential and commercial areas
- Frequent congestion during peak hours
- Critical for economic and commercial activity
Upgrading this route will reduce travel time and improve daily commuting for thousands of residents.
Completion Timeline: Four Months Target
Officials have confirmed that the project will be completed within four months, provided there are no major disruptions.
Factors Supporting Timely Completion
- Approved funding
- Clear work segmentation
- Experienced contractors
- Continuous supervision
The government has emphasized strict monitoring to ensure deadlines are met.
Addressing Allegations About Project Approval
Recent media reports raised concerns that the project’s approval violated financial and administrative regulations.
Allegations Raised in Media
- Project divided into eight packages
- Alleged attempt to bypass Provincial Development Working Party (PDWP)
- Questions over transparency
These claims created confusion and public debate.
Officials Reject Allegations and Clarify Facts
Project officials strongly rejected the allegations and clarified that the segmentation of the project was done strictly according to rules.
Official Explanation
- Project division aligns with Annual Development Program (ADP)
- Segmentation improves efficiency
- Better resource utilization
- Faster execution
Officials stressed that there was no violation of rules or procedures.
Why the Project Was Divided Into Eight Packages
Dividing large infrastructure projects into multiple packages is a common and accepted practice.
Benefits of Project Segmentation
- Faster execution
- Better contractor management
- Reduced risk of delays
- Improved quality control
This approach allows different sections to progress simultaneously.
Tender Cancellation and Rs 900 Million Savings
The first round of tenders for the Multan Avenue project was cancelled due to temporary funding shortages.
What Happened Next
- Revised financial planning
- Improved tender process
- Competitive bidding
As a result, the second round of tenders led to savings of Rs 900 million compared to the initial attempt.
Transparent Tendering and Technical Approval
Officials confirmed that all work packages were:
- Technically vetted
- Approved through proper procedures
- Awarded transparently
This ensured financial discipline and accountability throughout the process.
Role of NESPAK and Administrative Oversight
The execution of the project is being supervised by NESPAK, Pakistan’s leading engineering consultancy.
Oversight Structure
- NESPAK: Technical supervision
- Divisional Commissioner: Administrative oversight
- Regular inspections
- Compliance with approved specifications
This multi-level monitoring system ensures high construction standards.
Expansion of Dual Carriageway to Six Lanes
One of the most significant upgrades under the Multan Avenue project is the expansion of the dual carriageway.
Road Expansion Features
- Three lanes in each direction
- Increased traffic capacity
- Reduced congestion
- Improved driving comfort
This expansion will support future traffic growth.
Dust-Free Surface With Tuff Pavers
To address air pollution and dust issues, the project includes the installation of tuff pavers.
Benefits of Tuff Pavers
- Dust-free road surface
- Increased durability
- Lower maintenance costs
- Improved road cleanliness
This feature is especially important for urban health and environment.
Installation of Modern LED Streetlights
The project includes 260 modern LED streetlights along the entire route.
Advantages of LED Streetlights
- Better night visibility
- Energy efficiency
- Reduced electricity costs
- Improved road safety
Well-lit roads significantly reduce accident risks.
16-Feet-Wide Service Roads on Both Sides
Service roads are a key feature of the project.
Benefits of Service Roads
- Separate local traffic
- Reduced pressure on main road
- Better access to shops and homes
- Improved traffic management
Each service road will be 16 feet wide.
Pedestrian-Friendly Walkways and Medians
The Multan Avenue project places strong emphasis on pedestrian safety.
Pedestrian Infrastructure
- Safe walkways
- Paved medians
- Organized crossings
- Reduced accident risks
This makes the road safer for walkers and cyclists.
Organized Parking for 1,890 Vehicles
Unplanned parking has been a major cause of congestion in Multan.
Parking Facilities Included
- Parking for 1,890 vehicles
- Organized parking zones
- Reduced roadside parking
- Smoother traffic flow
This will greatly improve urban mobility.
Iconic Monuments and Urban Aesthetics
Beyond functionality, the project focuses on urban beauty.
Aesthetic Enhancements
- Iconic monuments
- Decorative elements
- Improved city image
- Tourist-friendly environment
These features will enhance Multan’s identity.
Green Corridors and Sustainable Development
Environmental sustainability is a key pillar of the project.
Green Infrastructure Highlights
- 14-feet-wide green corridors
- Service road landscaping
- Shade trees
- Improved air quality
Green spaces promote healthier urban living.
18 Kilometres of Landscaped Parkways
The project includes 18 km of continuous landscaped parkways.
Recreational Features
- Walking tracks
- Benches
- Ornamental lighting
- Family-friendly spaces
This transforms the road into a community space.
Relocation of Electricity Poles for Safety
Electricity poles will be relocated to the Right of Way (ROW) boundary.
Benefits of Pole Relocation
- Improved road safety
- Reduced accident risks
- Lower future maintenance costs
- Long-term cost efficiency
This step ensures better infrastructure planning.
Economic and Social Impact of the Project
The Multan Avenue project will deliver multiple benefits.
Key Impacts
- Faster travel times
- Reduced fuel consumption
- Job creation
- Improved business activity
- Enhanced quality of life
The project supports both economic growth and social wellbeing.
Setting a Benchmark for Urban Development
Officials believe the Multan Avenue project sets a new benchmark for urban infrastructure in Pakistan.
Why This Project Stands Out
- Integrated planning
- Environmental focus
- Community-friendly design
- Transparency and efficiency
It serves as a model for future projects.
Public Response and Expectations
Residents and public circles have welcomed the project enthusiastically.
Public Expectations
- Timely completion
- Quality construction
- Minimal disruption during work
- Long-term maintenance
Authorities have assured that these concerns are being addressed.
Conclusion
The Multan Avenue project, with a cost of Rs 2.8 billion and a four-month completion target, represents a major step forward in modern urban development. From wider roads and LED lighting to green corridors and pedestrian facilities, the project combines infrastructure growth with environmental and community-friendly planning.
Once completed, Multan Avenue will not only ease traffic congestion but also enhance the city’s beauty, safety, and livability—setting a strong example for urban projects across Pakistan.
FAQs About Multan Avenue Project
What is the Multan Avenue project?
The Multan Avenue project is a major road infrastructure development approved by the Multan Divisional Development Working Party (DDWP) to upgrade a 9-kilometre road in Multan.
What is the total cost of the Multan Avenue project?
The total approved cost of the Multan Avenue project is Rs 2.8 billion.
What is the route of the Multan Avenue project?
The project stretches from Saidanwala Chowk to Sahu Chowk in Multan.
When will the Multan Avenue project be completed?
Officials expect the project to be completed within four months, subject to smooth execution.
Why was the project divided into multiple packages?
The project was divided into eight packages to improve efficiency, manage resources better, and align with the Annual Development Program (ADP). Officials have denied any violation of rules.